The Silverton High School project is taking place on a 9th grade only campus that is being converted into the towns new 9-12 campus.
An original schedule of 24 months has been reduced to 18 months through the utilization of an early site winterization package. Key features of this project include:
- Two-story classroom addition
- Gymnasium addition
- 500+ seat full-featured auditorium
- Media center
- Commons
- New administration area & admin remodel
- Parking lot expansion, and
- New athletic fields
The Silverton High School construction schedule is April 2007 – July 2009.